Performance Contracting at FCC
Scope of Work includes:
Minimizing the Kiln Room AHU operating conditions. The existing AHU is programmed to operate continuously during the scheduled occupied times and maintains typical heating/cooling set points.
- Re-classifing the AHU operation to an un-occupied (storage area) sequence of operation.
- Scheduling t he AHU fan to run continuously only when either of the Kiln exhaust fans are energized.
- Adding exhaust fan interlock relays to provide binary input demand for continuous AHU fan operation, including mounting & wiring of relays and re-programming of local JCI DDC controller.
|
|